Retour aux références

Energy & industrial

Shell Gas Station

Petroleum infrastructure

Mission G1Mission G2Mission G5

Localisation

Industrial zone, Nador

Année

2023

Durée

8 months

Client

Shell Morocco / Vivo Energy

Shell Gas Station

Contexte du projet

Next-generation gas station located in Nador industrial zone, including 6 storage tanks of 50m³ each, 8 distribution islands, shop and car wash area. The site has strict environmental constraints related to soil and groundwater pollution risks.

Défis géotechniques

  • Shallow water table (3-4m) requiring special precautions
  • Strict environmental regulations (water table protection)
  • Stability of underground tank pits in presence of water
  • Heavy traffic loads and dynamic solicitations

Solutions mises en œuvre

  • 1Detailed hydrogeological study with water table flow modeling
  • 2Waterproofed pits with HDPE geomembrane and drainage system
  • 3Reinforced concrete slab sized for heavy loads (40T trucks)
  • 4G5 system implementation: piezometers for water table quality monitoring

Livrables & documentation

  • G1 Report: Geological synthesis and hydrogeological study
  • G2 Report: Sizing of pits, slabs and drainage system
  • G5 environmental monitoring plan and monitoring protocol
  • Technical specifications for waterproofing and materials

Chiffres clés du projet

Tanks 50m³

Double wall with leak detection

Piezometers

Continuous water quality monitoring

%

Compliance

Shell environmental standards